NEWS
October 19th, 2022
1. THE SCOW BELT PLAN:
• Oct. 18: New tail drum to arrive on site
• Oct. 19: Installation of new tail drum (Afternoon Millwrights)
• Oct. 20: New belt to be installed and vulcanized (Contractors)
• Oct. 21: Belt to be tracked and tested (Contractors and Millwrights). Scow to be loaded after all work is completed.
• The tail drum will be installed the 19th on afternoon (after production).
2. SAWMILL SCHEDULE
• October 14, 2022 – Down
• October 17, 2022 – Run
• October 18, 2022 – Run
• October 19, 2022 – Run
• October 20, 2022 – Down (New belt to be installed and vulcanized (Contractors)
• October 21, 2022 – Down (Belt to be tracked and tested (Contractors and Millwrights). Scow to be loaded after all work is completed.)
• October 24, 2022 – Run
• October 25, 2022 – Run
• October 26, 2022 – Run
• October 27, 2022 – Run
• October 28, 2022 – Down (Clean Up)
3. PLANER SCHEDULE
• October 24, 2022 – Run
• October 25, 2022 – Run
• October 26, 2022 – Run
The company has not announced any schedule or plans for the week of October 31st.